SECOND SPAN BLUE WATER BRIDGE
BRIDGE STATISTICS


photo courtesy of Vanderhoeven Photography

  Existing Bridge New Bridge
Type of Bridge Cantilever Truss Continuous Tied Arch
Total length of Bridge, excluding plazas 6,534' 6,109' (1862 m)
Number of spans 72 39
Main span length 871' 922' (281 m)
Truss/Arch length 1,576' 1,480' (451 m)
Width 40' 51' (15.6 m)
Lanes/Width 3/10'-8" 3/12'
Total weight of main span 28,340 tons 20,084 tons
Total weight of American approach 9,940 tons 30,591 tons
Total weight of Canadian approach 11,050 tons 33,353 tons
Total weight of steel and concrete 86,905 tons 84,028 tons
Rivets 2,228,000 (500 tons) ---
Bolts --- 350,000
Steel foundation piling --- 31 miles (50,302 m)
Clearance above river 152' 155'
Top of steel above river 210' 233'
Main pier construction Each main pier contains 10,000 tons of concrete & reinforcing steel resting on rock Each main pier sits on 144 H-piling driven 105' to bedrock
Construction Commencement 6 - 24 - 37 6 - 15 - 95
Main span steel joined 5 - 24 - 38 11 - 8 - 96 (proposed)
Completion 10 - 10 - 38 7 - 1 - 97 (proposed)
Cost of Construction $3,250,000 $79,269,755
Total Construction $3,900,000 $107,488,651
     
(Construction, Ferries, Engineering, Right of Way, Environmental Activities, etc.)
     
Construction Cost per Total Cost 83 % 74 %
Source of Funding Michigan: State (incl. main span) / Federal

Ontario: Province / Federal

MDOT and FHWA

BWBA / Bank of Nova Scotia

Tolls $0.60/car & driver
$0.10/passenger/pedestrian
$1.50/car
$2.00/axel/truck